Thursday, December 16, 2010

Free Lodger Agreement Template

day 88

This morning I was again able to go into the air.
When I read in another building diaries that there was with the Hausanschlüßen such problems, I really thought that we have the will not happen. How naive I was. Yes, I would like to swing the ax * * winkzuRina

So ... the man of Eon has installed the meters not . Our electrician (who also is master!) Has tried to persuade him, I was wondering what I need, so that it incorporates the counter or even daläßt that the master electrician installs it then. No, he was stubborn and went away empty-handed. Our electrician (and me) was really angry. Thus, a bean counter. He is supposedly not allowed and bla bla bla ...

The men of the company that will put us to the terminal building were also back, and have worked ...





If I, however, the work ethic of some people so listen, then I could really go off too far. When our electrician

asked them when they are actually ready, says one, "If the weather is still a bit worse, then we stop!" We just looked and said nothing. Of course it's cold and it also has very little snow ... but that's why you have not stop yet.

You can tell so very well that these poor sausages know that she has the upper hand. I can not eat as much as I would like to kot * en * Sorry *

My conclusion of the last days to subsequent owners with basement ...

If you asked the Hausanschlüße, then asks on the phone all the way to specifically what you must do yourself also waived if you own on performance! asked, according to the size of the core hole, let yourself be confirmed in writing, asks about the poem. So that you also have everything ready and in place when people come and open the ditch! Doing nothing and you stand there like stupid!

For so slowly I can see really that we have a problem! Fortunately, we do not have to 22.12. chosen as moving day, but for us the 28.12. decided. Not to us, our electrician (if the house connection is finally in the house and the fitter of Eon with the counter not rankommt) also make the Baustromzähler into the house. So, we first have electricity at all in the house and not get an extension cord to power the street into the house.

Man, man, man ... I could really bring out the ax! After

at 12:15 clock we have the date for a blower door test. I'm curious how far will the "good" people with their graves are.

tonight then comes the rest of the day ...

Now it sleeps 20:00 clock, the Lütte and I feel much better again! All morning I had stomach pains and I was not really good. This helplessness makes a truly all.

I am shortly before 12:00 clock back to the house and was so tense that the people have now really stopped. It was after all the snow and it was icy wind. But they were still there and still working !!!!!! I was soooooooooooo easy! One man came up to me and said that I can really lucky that they have not stopped. I was so grateful that, even if it's their job. The cables are now in the basement ...






It now both cables are pulled through! However, I am now again a little annoyed. The man that makes the day even now, has asked me if the meter then the last ditch to leave, because still the missing seal must be attached (coming eventually). When I asked him if that is appropriate for from the outside, he said "Yes!". He has recommended to me as a skilled worker is this that open later in the back of the trench the pipe is not damaged, I agreed. Tonight on the phone but said our construction manager, that this seal is placed from inside . Well, what now?? Since our construction manager has said yes but now what we ever wrong, keep up the last meters, as put a tarp over it and a menu and wait to go on, until the seal is! To my child, I would now probably say "I have the fax thick!" * Laughs *

When I was there at noon and have dropped in for the blower-door test, which was there maybe a bustle in the house. For in addition to the painters are also been there the carpenters who built the doors ...





be the today, even if complete, but there are still missing, the door handles that are only delivered and installed next Wednesday.

And then came the man who made the blower door test ...








During the actual test, I unfortunately could not attend because I had to pick up the Lütten.

was finally sawn our stairs to the attic right that you could use them too ...


Rauspund and was brought to the attic and nailed ...



were then still the wood strips and then attached gemalert hard. The basement walls are now all white and it all looks much brighter and friendlier.

The missing piece of the stairs and was now also placed equal moored.

Tonight was our so called construction manager and said, that our futures move tomorrow for a little pre-acceptance must because he allegedly because the weather is not so well. I assume no one wants something, but so slowly I get the crisis because of this acceptance. Instead we meet at 10:00 clock now at 13:00 clock in the house. He wants to call even when he just wants to arrive. I think yes that he simply preferred a different house and we were so moved by behind. When you enter the weather as a reason one can say as the owner do not mind, eh. We had this all planned out, also because our friend. Namely, the afternoon had no time. But he has made it possible, and his appointment that he had at 13:00 clock, moved because of us. It was so important that he is there and luckily he is now.

I'm sitting here and I'm really just annoyed and totally hooked. Sometimes I feel correctly processed here cht * *. On Monday, the final inspection is then also only the pure site visit, if only so much will be made on Tuesday and Wednesday. The Protocol will be very often "could not be verified!" Whether this is referred to Viebrock ... I do not know.

What I said one construction worker today ... Viebrock has cracked this year, the number 1750 (with Austria, and Switzerland together). Well, we just do not fall so much of ...